Supply Chain Action Points
Read this first — the conclusion, and the moves to make:
- This month, ask every shortlisted building for three numbers in writing, dock doors, appointment window length and trailer pool size, and strike any site below roughly one door per 10,000 square feet unless there is a documented second-shift plan.
- Before signing anything longer than 24 months, model cost per pallet-turn on your peak week rather than your average week; if the inland option needs a second building to match throughput, book the rent saving as negative.
- Book receiving appointments for the peak build eight weeks ahead and leave 15% of each week's slots unbooked as buffer, released 72 hours out.
- Put an accessorial cap in the contract: name a maximum average trailer wait of 24 hours, with a review clause that triggers renegotiation if it is breached two weeks running.
- Re-check the submarket every quarter rather than annually, and treat the landlord's own demand commentary, not the vacancy print, as the leading indicator.
Prologis reported US warehouse vacancy eased in Q1 as restocking resumed ahead of peak season. The logistics landlord said demand concentrated near gateway ports and inland rail hubs, lifting rents modestly.
The Analysis
A warehouse is not a building. It is a number of doors, a patch of yard and a shift roster, and of those three the building is the least interesting. Prologis published its first-quarter read and the headline was that US warehouse vacancy eased as restocking resumed ahead of peak season. Demand, the landlord said, concentrated near gateway ports and inland rail hubs, and rents lifted modestly.
I have stood in enough yards watching trailers wait for a door to be suspicious of the word modestly. Rent is the number that gets negotiated in a boardroom and then sits still for five years. The number that moves every week is the one nobody puts in a press release: how long a container sits on a chassis because the receiving dock has no appointment, how many times a truck can get in and out in a shift, and whether there is room in the yard for the trailer that showed up four hours early.
For an importer building stock for peak, this is the quarter where a decision gets locked in that you will live with for two or three years. Not because vacancy moved a point, but because everyone is about to sign at the same time, in the same four submarkets, off the same quarterly print.
Read the vacancy figure for what it is. It is net absorption against new supply, counted in square feet, averaged over a national stock that runs from forty-year-old sheds with twenty doors to new buildings with sixty. It tells you what share of the country's industrial floor space is empty. It does not tell you whether there is an empty building with the door count, the clear height, the power and the yard your cargo needs, in the submarket where your containers actually land. The useful sentence in the report is not the vacancy number. It is the one about where demand concentrated.
That concentration is not mysterious. Restocking ahead of peak is a speed problem wearing a storage problem's clothes. When you rebuild inventory on a short clock, the cost of distance stops being rent per square foot and becomes turns per week. A building fifty miles inland can be cheaper on the lease and more expensive on the pallet, because every container that lands has to make a longer drayage run to get there, and the dock door that receives it cycles fewer times in a shift. You are not buying space. You are buying the number of times a week a box goes from a chassis to a rack and the chassis leaves.
Who feels this first depends on what they own. An importer with a dedicated building, its own yard and a labour plan feels it at renewal and in wage competition, and can usually absorb both. An importer running through a third-party warehouse feels it within weeks, because a tight market reaches them as an accessorial schedule: appointment fees, waiting time, extra handling, a surcharge for anything that lands outside the booked window. The small importer feels it as absence. There is no space at any price in the right submarket, so they take the wrong one, and the penalty is paid in drayage and in replenishment that runs two days behind the sales plan. On the export side the same squeeze arrives from the other direction: export cargo wants the same chassis, the same gates and the same drayage capacity at the same gateway, and when import restocking pulls hard, the export booking is the one that gets rolled.
The timing is not uniform, and that is what catches people. Rent moves at renewal, which for most tenants is twelve to thirty-six months out, so the lease you sign in the next eight weeks is the one that sets your cost through 2029. Accessorials move in weeks. Labour moves slower than either, because a certified reach-truck operator is not something you order alongside the racking.
Here is the part the report cannot say, because it is not in the dataset. Restocking ahead of peak delivers inventory before it delivers people. A container can cross an ocean and clear in less time than it takes to post a job, screen, badge and certify a forklift operator in a market where every warehouse within thirty miles is hiring at once. So the queue does not form at the racking. It forms at the receiving dock and in the appointment book, and both are invisible in a vacancy rate.
The second thing the number hides is the metric you should actually be managing. Rent per square foot is a real estate metric. Cost per pallet-turn is an operating metric, and once demand has concentrated around a handful of gateways, the second one is where the money is decided. A building with sixty doors and a shallow yard can beat a building with thirty doors and a deep yard on the same lease rate, and the lease rate will never tell you which one you have.
Put numbers on it, and take these as my assumptions, not as anything from the report. You need 180,000 square feet. The port-adjacent building is quoted at $8.40 per square foot per year; the one fifty-five miles inland is $6.30. On the lease alone the inland building saves $378,000 a year. Now assume the port building's doors cycle twice as often in a week, because the drayage round trip is short and the truck can come back the same shift. To move the same weekly container count out of the inland building you need roughly double the doors, and in a standard configuration that means roughly double the footprint: $6.30 against 360,000 square feet is $2.27 million, against $8.40 on 180,000 square feet, which is $1.51 million. The cheaper building costs $750,000 more a year in rent alone, before one extra mile of drayage. That arithmetic never shows up in a rent-per-square-foot comparison, and it is the only comparison that survives contact with a peak season.
The traps are consistent. Signing a five-year lease off a quarterly print is one; the print is a snapshot of a market already in motion, and the leverage in that negotiation belongs to whoever holds the empty building, which may not be your landlord. Reading modest rent growth as modest renewal terms is another; the average is modest, and your specific building may be the one with a queue at the gate. The third is contract shape. In a tight submarket the money does not appear in the base rate, it appears in the accessorial schedule and the appointment rules, and those live in an annex nobody reads until the first detention invoice lands.
So before you tour another building, ask for three numbers in writing: doors, appointment window, trailer pool. If a broker cannot produce all three, you are being shown floor space, not capacity, and floor space is the one thing this market still has.
↑ Back to the key points