Supply Chain Action Points
Read this first — the conclusion, and the moves to make:
- Within thirty days, count trailers on site per day for the last ninety days and write the busiest single day into your space requirement as a hard number, not a range.
- Before any signature, verify dock doors and trailer positions on the site plan, and require exclusive use of a stated number of positions in the lease rather than a shared-yard clause.
- Negotiate concessions instead of headline rent while rents hold firm: target three months of free rent plus the trailer positions, and treat tenant improvements as the second lever.
- Sequence the build-out against the goods: book racking, fire sign-off and labour recruiting immediately on signature, and refuse an arrival date inside sixty days of handover.
- Decide the submarket inside the first quarter, because stabilised vacancy means the usable buildings get allocated within roughly a month once tenants stop waiting.
Prologis reported US warehouse vacancy stabilising as the year opened, with restocking demand near gateway ports and inland rail hubs. The logistics landlord said rents held firm after the prior year's correction.
The Analysis
Prologis reports US warehouse vacancy stabilising as the year opened, restocking demand clustered near gateway ports and inland rail hubs, and rents holding firm after last year's correction. Three clauses, no figures. Each one describes a different constraint, and they do not all bind in the same month.
Vacancy is counted in square feet. A warehouse actually runs on dock doors per shift and trailer positions in the yard. Those two numbers can point in opposite directions inside the same submarket, and January is when the gap between them opens.
The building I would worry about is not the empty one. It is the good one, the one with the doors and the yard, which is quietly full while the average still reads calm.
Take the vacancy figure apart before you use it. A stabilised average across a market is an average across two very different stocks. Buildings that work, meaning enough doors, a yard deep enough to turn a trailer, a cross-dock layout and usable clear height, are effectively taken. Buildings that do not work stay empty and hold the average down. You end up with two markets and one number, and the number is the one planners budget against. That is the first thing that goes wrong in a year like this one, and it goes wrong quietly, because nobody publishes the split.
The physical sequence inside a distribution centre runs doors, then yard, then labour, then rack. A signed lease is not capacity. Capacity begins when the racking is up, the fire system is signed off, the permit is closed and enough people have been hired to run two shifts. In my experience that is two to three months from signature, and that is my own rule of thumb rather than anything in the release. Restocking demand does not arrive on a two-to-three-month clock. It arrives when the purchase orders land. So the mismatch is structural: the lease clock and the goods clock run at different speeds, and January is when both start.
Clustering makes it worse, because restocking near gateway ports and inland rail hubs is not a diffuse demand. It is demand for the same twenty-mile radius, the same drayage fleet, the same chassis pool, the same drivers, the same warehouse labour market. A building near a port competes for trucks with the export empties being staged in the same yard, which is a detail that bites export shippers who think a warehouse story is not their story. When the yard fills with import trailers waiting for a door, the empty container that was supposed to be picked up on Tuesday is still sitting in the third row on Thursday.
Size decides which end of this you are on. A multi-site importer can shift volume between buildings and absorb a slow door for a month. A mid-size importer with a single building near a gateway port is the one bidding against three others for the only eight-door building with a usable yard, and losing politely. A small importer working through a third-party warehouse is not in the bidding at all: the space it depends on has already been committed to somebody else's contract, so at the first restocking push the answer is a peak surcharge or a straight no, delivered late. Direction matters too. Importers feel this on the receiving door and the appointment book. Exporters feel it on the empty pick-up and the cut-off, because their boxes are staged in the same yard that is now full of somebody else's imports.
The timing is what most people get wrong. Restocking leases get signed in January and February for goods that arrive in spring. The pain shows up six to ten weeks after signature, when the pallets are on the floor and the racking is still in crates, and it shows up a second time at the first real peak, when appointments fill and trailers start parking because there is nowhere to put them. The yard is the warehouse nobody leases and everybody uses.
What the release does not say is that the yard is unbilled inventory, and it is the constraint that cannot be fixed by renting more racking. Every trailer waiting for a door occupies a position, and positions live on the site plan, not in the rentable area you negotiated. A 200,000 square foot building can be operationally full at 85 percent occupancy if the doors and positions are saturated, and that number never appears in a vacancy statistic. There is a second thing hiding behind rents holding firm. When the headline rent stops moving, the negotiation moves to concessions: free rent, tenant improvements, and the one that actually pays, additional trailer positions with exclusive use written into the lease.
Landlords defend the published rate because it sets the comp for the whole asset, and give away term and parking because those do not print in the brochure. Ask for the positions, not the discount. The third piece is the signal itself. Stabilised vacancy means stop waiting, and when every tenant stops waiting in the same month, the good buildings go from negotiable to allocated in about a month, which is faster than any approval cycle inside your own company.
Run the numbers with my assumptions, not the release's, since it gave none. Take a 200,000 square foot building with twenty doors on a single shift. Assume eight productive hours per shift and ninety minutes average per trailer at the door. That is a hundred and six door-slots a day on paper, and at a realistic seventy percent you plan about seventy-four appointments. Restocking pushes you to ninety-five trailers on a peak day, so twenty-one trailers have no appointment and they park. At an assumed eighteen hundred square feet per trailer position including aisle, those twenty-one trailers need roughly thirty-eight thousand square feet of yard, close to a fifth of the building footprint and none of it in your rentable area. If the site plan allows fifteen positions, you are short on day one of the peak and the overflow ends up on the street, which is a municipal notice waiting to happen. Every figure in that paragraph is my assumption, not a number from the report.
The counterfactual is uncomfortable, because waiting feels prudent. Wait for the rent to fall and you will get the cheap building with eight doors and twelve trailer spots, and you will pay the difference in detention and missed appointments for the whole lease term, which is three to five years of a decision made in one afternoon. Take the good building at firm rent and skip the yard negotiation, and you get the same failure at the first peak with a higher base rent. Move inland for cheaper space and you are trading drayage miles for rent, which is a legitimate trade, but it only works if your cargo is not restocking against a port arrival date.
The trap is measuring the market instead of the building. Market vacancy, rent per square foot, and a broker's view of the submarket will all look fine while the only building you can actually use has no doors and no yard. The action that costs nothing today is to count your trailers per day for the last ninety days, take the single busiest day, and put that number into your requirement with a hard floor attached: this many doors, this many exclusive trailer positions, verified on the site plan before signature. If the site plan cannot hold your peak day, the rent is irrelevant. You cannot park a truck in a discount.
↑ Back to the key points