Supply Chain Action Points
Read this first — the conclusion, and the moves to make:
- By 21 August 2026, log berth waiting time for every lane you ship, using the Week 32 baselines of 87 hours at Shanghai and 36 hours at Ningbo, and convert Shanghai's 87 hours into 3.6 days inside the transit promise you quote to customers; trigger the backup port the same week any lane's waiting time passes 96 hours.
- By 23 August 2026, pull every shipment scheduled for the rest of August forward by five to seven days, with the target of having 90% of August volume tendered before 26 August, because one three-day terminal stoppage on an assumed 20 containers a month hits about two containers, roughly 9,000 dollars at the assumed 1,500 dollars a day.
- By 31 August 2026, book a Ningbo diversion trial of three containers or 15% of monthly volume, whichever is smaller, for four weeks, against an assumed extra 220 dollars of drayage and an assumed 2.1 days saved worth about 3,188 dollars, targeting roughly 2,970 dollars net per container and holding on-time delivery at or above 92%.
- By 15 September 2026, review the locked share of intra-Asia volume against the index rather than against last quarter's rate, and cut it to 30% while Drewry's expectation of stabilisation in coming weeks holds, because the index is at a six-week high; drop to 15% if it falls two weeks running, and go back up to 50% if a fourth storm forms or Middle East tension escalates.
- By 30 September 2026, write the air escalation rule as a hard threshold: release air only when expected delay days multiplied by the assumed 25,000 dollars a day line-stop cost exceeds the assumed 73,247 dollars a container gap between sea and air, which works out at roughly three days of delay.
- Set a standing Monday review of three numbers you own rather than the index: berth waiting hours on your two main lanes, your own rolled-container rate over the trailing four weeks, and actual versus planned gate-in days, and if the rolled rate passes 5%, replace the cheap booking or add a sailing.
Drewry's Intra-Asia Container Index rose 6% to USD 1,028 per 40ft box, a six-week high, as Typhoon Dolphin and Middle East tensions tightened capacity. Shanghai-Jawaharlal Nehru surged 33% to USD 2,353, while Shanghai-Singapore gained 8% to USD 1,096.
The Analysis
The line I keep in my head for this part of the world runs Shanghai to Ningbo to Keelung, down past Hong Kong and Singapore to Port Klang, out to Tanjung Priok and Laem Chabang, and west to Nhava Sheva. When a number moves on that map I do not look at the number first. I look for which node on the map is hurting, because the map is what actually decides whether your container sails. Drewry's Intra-Asia Container Index went up 6% this week to 1,028 dollars per 40-foot box, a six-week high and the second weekly rise in a row, and the two reasons printed alongside it are both physical: Typhoon Dolphin, the third and strongest storm to hit China in five weeks after Bavi and Noul, and continued tension in the Middle East. Inside the same report sits the figure that should worry you more than the index: average vessel waiting time in Week 32 reached 87 hours at Shanghai.
Eighty-seven hours is three and a half days of a ship doing nothing, and that is not a pricing story, it is a node story. Add the roughly 2.4 million TEU of containership capacity currently waiting outside Chinese ports and you have a picture of a network where the schedule is fiction. Shanghai terminals and other regional facilities imposed restrictions and temporary suspensions as the weather deteriorated. In Keelung, strong winds toppled seven containers at Yang Ming's yard, some of them into nearby cranes. Cranes are the machine that loads your box, and when the wind can stop the crane, the crane is the bottleneck, not the rate.
I will leave the freight rate mechanics to people who do that for a living. My job here is the road, or in this case the water road, and what I want to know is which port is passable this week and what it costs you to move around the one that is not. The numbers I am working from are the ones in the report: 1,028 dollars on the index, up 6%; Shanghai to Nhava Sheva up 33% to 2,353 dollars; Shanghai to Singapore up 8% to 1,096; Shanghai to Jakarta up 5% to 1,533; Ho Chi Minh City to Shanghai up 14% to 74 dollars; Laem Chabang to Shanghai up 6% to 234 dollars; 87 hours waiting at Shanghai and 36 hours at Ningbo in Week 32. Drewry expects rates to stabilise in the coming weeks. That expectation and those waiting times are pulling in different directions, and the gap between them is where your decision sits.
Start with the two waiting times, because they are the most useful pair of numbers in the whole report and almost nobody reads them together. Shanghai at 87 hours and Ningbo at 36 hours are 51 hours apart. Fifty-one hours is 2.1 days. If you are booking out of Shanghai on reflex, and most people are, you are standing in a queue that is 2.1 days longer than the queue one port down the coast. Now put a price on that time. Assume a delayed container costs you 1,500 dollars a day in stockout, expediting or line-down cost, which is my assumption and you should replace it with your own. Two point one days of that is about 3,188 dollars per container.
Compare that with the rate move everybody is talking about. Shanghai to Singapore went up 8% to 1,096 dollars, which means it was about 1,015 dollars before, so the increase is roughly 81 dollars a container. The waiting time costs you 3,188 dollars per container and the rate increase costs you 81. That is thirty-nine times more. I know which one I would spend this week on. The index going up 6% is what gets written in headlines; the ship sitting still for three and a half days is what turns into a missed production window and a phone call you do not want to take.
The Nhava Sheva lane is a different animal and deserves its own arithmetic. Shanghai to Jawaharlal Nehru rose 33% to 2,353 dollars, which implies roughly 1,769 dollars before the move and a difference of about 584 dollars a container. Assume you run 20 containers a month on that lane, my assumption, and the lane just got about 11,677 dollars a month more expensive. A 33% weekly move on a single lane is not a gradual tightening, it is someone pulling capacity out of the lane, and when that happens the thing that follows the rate is the schedule. On a lane moving like that I would stop treating the published transit time as real and start adding a buffer measured in days rather than hours.
Then there is the weather, and the weather has a rhythm you can plan against. Dolphin was the third storm to hit China in five weeks, after Bavi and Noul. Three storms in five weeks is not bad luck, it is a season, and a season has a shape: you get a storm, operations stop or slow, the backlog builds, the backlog clears, and then the next one arrives and you do it again. Assume one storm suspends terminal operations for three days, my assumption. Assume you ship 20 containers a month and that three days out of thirty puts about 10% of your monthly volume in the affected window, so two containers. Two containers delayed three days at 1,500 dollars a day is about 9,000 dollars a month. That is the real cost of a storm, and it is paid in time, not in freight.
Now the 2.4 million TEU sitting outside Chinese ports. I do not have a clean way to convert that into your book, and anyone who tells you they do is guessing. What it tells me is simpler and more useful: when that much capacity is parked and waiting, the schedule your forwarder sent you is an intention, not a commitment. In that environment the cheap booking is the one that gets rolled. Rolling is the quiet tax of a tight market, you do not see it on the rate, you see it when the container misses the vessel and the vessel you wanted is now full. Ask your forwarder for your own rolled-container rate over the last four weeks before you ask them anything about price. If you cannot get that number, you are buying blind.
There is one more node that never appears in the index and should. Most intra-Asia boxes do not ride one ship end to end. They ride a mainline vessel to a hub and then a feeder to the final port, and the feeder network is the part that breaks first when the weather moves through. If your Singapore cargo actually transships through Port Klang, or your Jakarta box comes off a mother vessel somewhere in the region, then your real exposure is not the berth at Shanghai, it is the connection. Ask the carrier one specific question this week: which vessel carries each leg, and what happens to the booking if the feeder misses the mother ship. Assume a missed connection costs four to seven extra days, my assumption, and you can see how the cheapest through rate on the table becomes the most expensive. When the network is this tight, a direct sailing with fewer touches is worth paying for.
Which brings me to the port switch, and this is the move I would actually test. Ningbo is showing 36 hours against Shanghai's 87. Assume moving your drayage from a Shanghai gate to a Ningbo gate adds 200 kilometres and about 220 dollars a container, my assumption, and assume the 2.1 days saved is worth 3,188 dollars at my assumed daily cost. Net is roughly 2,970 dollars a container in your favour. On 12 containers a month, also my assumption, that is about 35,640 dollars a month. Before you move anything, check the two things that can eat that: whether Ningbo has the sailing frequency you need on your specific lane, because a port with a short queue and one sailing a week is worse than a port with a long queue and four, and whether your cargo can physically reach Ningbo without turning the inland leg into its own project.
Test it small. Three containers, or 15% of the month's volume, whichever is smaller, for four weeks, with on-time delivery measured against the promise you actually made the customer and a floor of 92%. If the trial misses that floor, the port is not the problem and you should stop. If it clears it, scale to a third of the volume and keep the Shanghai gate warm, because you will need it back the week Ningbo gets its own storm. I have run this drill on land borders more times than I can count, and the rule is always the same: never close the old crossing until the new one has carried real freight through real weather.
The second lever is rhythm rather than geography, and it costs nothing. Ship five to seven days earlier than you have been shipping, for the next four weeks. That is not building extra inventory, it is moving the same orders earlier inside the same month, which is a different thing and mostly a matter of when the purchase order goes out. Assume the storm window sits in late August, which is a read of the season and not a forecast, and you want 90% of your August volume tendered before the last week of the month. What you are buying is a buffer against a three-day stoppage, and the buffer costs you a few days of carrying cost against a 9,000 dollar exposure.
The land side of a storm is its own problem, and it is the part everybody forgets. When terminals in Shanghai impose restrictions and temporary suspensions, the trucking does not pause politely, it stops, and then it all restarts at the same moment. Assume your binding constraint is the gate-in appointment rather than the vessel, which is usually true in a week like this: if the truck cannot get into the terminal before the cut-off, the sailing schedule is irrelevant to you. Two things help and neither costs money. Book gate-in appointments as early as the terminal system allows rather than on the morning you planned to load, and hold a 24-hour buffer between your planned gate-in and the carrier's documented cut-off. I have watched cargo miss sailings in ports between Izmir and Shenzhen for exactly this reason, and the story is always the same: the box was ready, the truck was ready, the gate was not.
Here is a piece of the report that I think most readers will skip and should not. Ho Chi Minh City to Shanghai is 74 dollars and Laem Chabang to Shanghai is 234 dollars, against 1,096 dollars the other way to Singapore. That spread is not an error, it is the shape of the trade: boxes want to go south and west far more than they want to come back north. If you have any volume moving in both directions, that is a card in your hand, and most shippers never play it. Take your northbound volumes to the same carrier that wants your southbound boxes, and ask for the pair to be priced together. I would not promise you what the answer will be, but I have never met a carrier who was indifferent to a customer who could fill the direction nobody else could fill.
There is also the transshipment question, which is worth pricing and nothing more. Shanghai to Singapore is 1,096 dollars and Shanghai to Jakarta is 1,533 dollars, a gap of 437 dollars. If your Jakarta cargo can move to Singapore and then onward, part of that gap is available to you, and part of it will be eaten by the transshipment fee, the feeder leg and the extra handling. I would ask for the through rate in writing and compare it against the direct sailing's actual transit, not its advertised transit. A cheaper routing that adds four days in a market where ships are already waiting 87 hours is not cheaper.
Air, because this is where the conversation always ends up when a port backs up. Assume a 40-foot box carries about 18 tonnes of your cargo, and assume air costs 4.20 dollars a kilogram on this lane. Both are my assumptions. Eighteen thousand kilos at 4.20 dollars is roughly 75,600 dollars, against 2,353 dollars by sea, so the switch costs about 73,247 dollars a container. Assume a stopped line costs you 25,000 dollars a day. Divide one by the other and you get about 2.9 days. That is your break-even: below roughly three days of expected delay, air loses; above it, air starts to make sense. Write that number down before the next storm, because in the middle of one everybody panics and nobody calculates.
I will add one option from my own patch, with a warning attached. If your cargo is moving between southern China and the Indochina peninsula, the land border crossings are a real alternative and a genuinely different road. I have spent years at these places and the rule is: never underestimate a border crossing. It can be the fastest thing you do all month, and it can be a three-day car park when a holiday, a scanner or a document mismatch lands on the same morning. Price it, run one trial, and do not build a plan that depends on it until it has carried freight through a bad week. It is a spare tyre, not a replacement engine.
And because a lot of people buy out of this region, think about what 3.6 days does to your replenishment maths. Assume your door-to-door from Southeast Asia normally runs 12 days, my assumption. Add the 87 hours of berth waiting and the effective lead time is about 15.6 days. Assume you consume 500 units a day at 8 dollars a unit, also my assumptions; carrying four extra days of cover ties up roughly 16,000 dollars of working capital. Now the other side of the trade: one three-day delay on a single container at my assumed 1,500 dollars a day is 4,500 dollars, and two of those in a quarter is 9,000 dollars. On those numbers the buffer pays for itself inside a quarter and keeps paying after that. Reset it when the waiting time comes down and not before, because a buffer you leave in place after the queue clears is just dead stock.
The Middle East leg of this deserves a sentence, because it looks remote from an intra-Asia booking and it is not. My reading of it is mechanical rather than political: when a distant lane gets risky, ships move more cautiously or take longer routes, and a ship that is five days slower somewhere else is five days of capacity that is not available here. I cannot prove that mechanism from this report and I will not pretend to. What the report does say is that rising fuel costs and continued Middle East uncertainty, including renewed hostilities and attacks on vessels, sat alongside the weather as reasons the rate move held. If you sign a three-month commitment this week, you are placing one bet on all three of those at the same time.
The traps are the ones that always show up after weather. The one that costs the most is the second congestion: the storm passes, everybody who was waiting releases their bookings in the same 48 hours, and the port that was already at 87 hours gets worse the week after the weather clears. Plan your release as if the backlog week is the tight week, because it usually is. The second is free time and demurrage, which quietly convert a port delay into a bill; know your free days at both ends before you reroute, not after. The third is assuming that because Drewry expects rates to stabilise in coming weeks, your schedule will stabilise too. Rates and schedules do not move together. Rates can fall while ships are still queueing, and your problem is the queue.
What would make me wrong is fairly easy to state. Drewry expects stabilisation in the coming weeks, and two things would deliver it: no fourth storm in the sequence, and no escalation in the Middle East, where renewed hostilities and attacks on vessels have kept sentiment cautious and pushed risk premiums into the market. Remove both and the 87 hours at Shanghai starts coming down, and a six-week high turns into a spike rather than a step. That is exactly why I would not lock a long commitment at this particular point in the curve. If the index falls for two consecutive weeks, cut your locked share and put the volume back on spot. If a fourth storm forms or the Middle East escalates, do the opposite and cover more, because the queue will lengthen before the rate does.
On who does what, and when. The logistics manager owns the port trial and the waiting-time log, with the Ningbo test booked by 31 August and a weekly record of berth waiting hours for every lane you use. Planning owns the five-to-seven-day pull forward, with 90% of August volume tendered before the last week of the month. Procurement owns the contract position, and I want the locked share of intra-Asia volume reviewed on 15 September against the index, not against last quarter's rate. Sales owns the promise, which means the transit times quoted to customers this week need the queue built into them rather than the timetable.
One last thing on the index itself, since it will keep moving and you will keep reading it. A 6% weekly move on a basket of lanes tells you the direction of the market and almost nothing about your own invoice. What tells you about your invoice is the waiting time at the port you actually use, the rolled rate on your own bookings, and the number of days between the gate-in you planned and the gate-in you got. I would take those three numbers over the index any week of the year. They are dull, they are yours, and they are the ones that tell you whether the road you are on is still open.