Peak-season rates stay elevated as SCFI extends six-week winning run

Source: Best Shipping · 2026-08-10 · 16 min read
中文

Supply Chain Action Points

Read this first — the conclusion, and the moves to make:

  1. By 31 August 2026, set the peak-season split at no less than 70% contract and no more than 30% spot, name an owner for the spot portion, and put a monthly review date in the calendar.
  2. Before the next tender award, index-link the contract to the Shanghai Containerized Freight Index with a monthly reset and a collar of about +15% and -10% around the base rate, with the index source and publication date written into the contract.
  3. Set minimum committed quantity at no more than 80% of forecast and request a one-month carry-forward of unused volume in writing, targeting agreement on at least 50% of committed lanes.
  4. By 15 September 2026, pull order-release dates for November shelf dates forward by four weeks against last year's plan, and hold goods at origin or in bond instead of buying premium October slots.
  5. Tag every Asia-Europe order with its actual routing, run two lead times, plan at the 20-day end of the 14-20 day range, and carry safety stock of at least 8 forty foot boxes, equal to six days of cover at 40 boxes a month.
  6. Put the pipeline cash line into the monthly cash forecast at 23 boxes and about 1.38 million dollars, using 40 boxes a month, 17 extra days and 60,000 dollars a box, and re-tender rather than renew if the diversion share falls below 60%.
Skip to the detailed analysis ↓
Summary

Entering August, the Shanghai Containerized Freight Index advanced for a sixth straight week as peak demand and tight capacity kept main-lane rates high. Over 85% of Asia-Europe ships still divert via the Cape, adding 4,000 nm and 14-20 days, while the Panama Canal holds a 14.78m draft limit.

The Analysis

A procurement desk can read six consecutive weekly increases and still ask the only question that belongs in its own budget: which line of my landed cost moves, and by how much? Entering August, the Shanghai Containerized Freight Index advanced for a sixth straight week as peak demand and tight capacity kept main-lane rates high. Over 85 percent of Asia-Europe ships are still diverting via the Cape, adding about 4,000 nautical miles and 14 to 20 days to a single leg, while the Panama Canal holds a 14.78 metre draft limit. Those are the facts. What follows is what they do to a buyer's cash and to the way I would sign a contract this quarter.

Six straight weeks tells me the direction. It does not tell me where the rise stops, and I do not trust anybody who quotes me a peak-season ceiling, because the ceiling is the one number in this market that has never once been right. What I can price is the structural part. Eighty-five percent is not a spike. It is most of the fleet taking the long way round, and it has been doing that long enough that I should plan on it rather than wait for it to end.

So I am going to break the cost structure open instead of arguing about the index. There are three places this lands: the cash tied up in the pipeline, the effective capacity the fleet can deliver across a year, and the cost of each box on a ship that cannot load to her marks. Ömer Kaya walks these corridors for a living; here I only price what they do to my landed cost.

Start by sorting the three facts, because they are not the same kind of fact. The six week streak is a direction. The 85 percent diversion figure is a structure. The 14.78 metre draft limit is a constraint. A direction tells you to move early. A structure tells you to change the plan rather than the price. A constraint tells you something about unit cost that no amount of negotiating will fix.

Here is the first piece of arithmetic, and I will mark every number that is not in the report as mine so that you can put your own in. Assume a European buyer moving 40 forty foot boxes a month out of Asia, assume 60,000 dollars of goods value in each box, and assume carrying cost at 10 percent a year. All three are my assumptions. The diversion adds 14 to 20 days to a single leg; take the middle, 17 days, also my assumption. A month is 30 days, so 40 boxes a month is 1.33 boxes a day, and 17 days of extra pipeline is roughly 23 boxes of stock that did not exist before, and did not exist permanently, sitting on the water rather than on a shelf or in a customer's hands.

Twenty-three boxes at 60,000 dollars is 1.38 million dollars of working capital, and at 10 percent a year that is about 138,000 dollars a year, call it 11,500 dollars a month. Nobody puts that line in a freight budget. It is the single largest cost of the diversion and it never appears on a freight invoice at all.

The range matters as much as the middle. Fourteen to twenty days is a six day spread, and a six day spread is not something you average, it is something you plan at the top of. Plan at 14 and the ship takes 20, and you are short six days of cover on every single arrival. On 40 boxes a month that is eight boxes, about 480,000 dollars of safety stock you have to hold just to survive your own plan. At 10 percent that is another 48,000 dollars a year. Plan at 20, hold the stock once, and stop paying for the same surprise every month. The discipline here is dull and it is the whole trick: take the pessimistic end of the range, write it into the lead time, and do not let anybody quietly put 14 back into the model because it makes the chart look better.

Buyers think in rates and finance thinks in totals, so here is the same thing said the way a finance director will ask for it, per box. Forty boxes a month is 480 boxes a year. Spread the 138,000 dollars of pipeline capital across 480 boxes and it is about 288 dollars a box. Do the same with the 48,000 dollars of safety stock carrying cost and it is about 100 dollars a box. Together that is roughly 388 dollars a box a year, against a box I assumed at 60,000 dollars of goods value, which is about 0.65 percent of the value of what is inside it.

Put that way it stops being a logistics complaint and becomes a margin argument, and margin arguments get funded. It also hands you a benchmark: any measure that takes days out of the pipeline is worth roughly 288 dollars a box for every 17 days removed, and that is the figure to sit next to a nearshoring proposal, an air freight quote or a buffer stock decision.

Now the part I have not seen written anywhere. Over 85 percent diverting means something like 15 percent are not. That is not a rounding error, it is two supply chains with materially different transit times running under the same purchase order book. If your buying team plans one Asia-Europe lead time across all of it, which most teams do, then 85 percent of your arrivals land late against the plan and 15 percent land three weeks early, and you end up with a warehouse that is short and full at the same time. The fix costs nothing. Tag every order with its actual routing, run two lead times, and set safety stock against each one. Averaging a lead time across two different populations is the most expensive free mistake in this market.

The Panama number is the one buyers skip, and they should not. A draft limit is a load limit wearing a nautical hat. A ship that cannot load to her marks sails with fewer boxes than her owner paid for, and the fixed cost of the voyage has to be recovered from those fewer boxes. The report does not give me a load effect, so I will invent one and label it: take 10 percent off the loadable boxes, my assumption and not a figure from the report. Recovering the same voyage cost from 90 percent of the boxes means each box carries about 11 percent more. That is a unit cost increase you cannot negotiate away, because the person across the table did not cause it and cannot remove it. It belongs in your cost model as a structural step, not as something to argue about at the tender table.

The largest effect of the diversion is not the days. It is what the days do to the fleet. A ship that takes 14 to 20 days longer on a leg completes fewer round trips in a year, and fewer round trips means the same fleet moves less cargo in twelve months. Assume a pre-diversion Asia-Europe round trip of 77 days, my assumption. Across 365 days that is about 4.7 round trips per ship per year. Add 28 to 40 days, which is the one-way penalty doubled, and you get 105 to 117 days, or 3.1 to 3.5 round trips. Capacity per ship per year falls to roughly 66 to 73 percent of what it was. To move the same annual volume you need somewhere between a third and a half more ships. That is what tight capacity actually means, and it is why a six week streak in August is not a bubble. It is arithmetic.

Standing on the buy side, this changes where the leverage sits, and I would rather say it plainly than pretend otherwise. I am not accusing anybody of anything. The ships are going the long way round, the canal will not take the draft it used to take, and both of those cost money that somebody has to carry. Leverage follows scarcity, though, and in week six of an increase running into peak season, scarcity sits on the other side of the table. Negotiating harder from that position gets you a worse outcome than changing what you ask for. Ask for space and for a formula, not for a number.

A streak does something specific to a buying organisation and it is worth naming. It produces a meeting. Somebody brings a chart, somebody else says the word peak, and the conclusion is usually that we should wait and see, because waiting has no line item attached to it. Waiting has a line item. Every week you delay a commitment during a streak, you buy that week's volume at that week's spot level, and this particular streak has moved in one direction six times. The cost of waiting is not the delay itself. It is the price you pay while waiting, and it never gets recorded, because it never looks like a decision.

There is one consolation inside the 85 percent figure and it is real, so I will take it. When nearly everyone goes the same way round, schedules get more uniform rather than less. During the period when the fleet was switching, one ship went one way and the next went the other, and the spread of arrival dates was miserable to plan against. With 85 percent on a single routing, most of your boxes travel on a comparable transit, and comparable transits are plannable. I would rather have a long, known, uniform road than a short road with a coin toss on it. It does not make the freight cheaper. It makes the planning honest, and honest planning is what lets the safety stock number come down.

So here is how I would structure it. On contract versus spot, a streak is precisely the moment when spot exposure is the expensive leg, because the streak is where the increases land. In a calm market I am comfortable carrying more spot than this. In week six of a rise, I am not. I would be looking at a contract share of around 70 percent of peak-season volume and leaving no more than 30 percent to spot, and I would concentrate that spot portion in the lanes and months where I genuinely have flexibility rather than spreading it evenly across the book.

On the formula, I want the contract tied to a published index rather than to a fixed number I have to renegotiate every quarter, because a fixed number in a streak stops being believed by the other side within about three weeks. Tie it to the Shanghai Containerized Freight Index, name the source and the publication date inside the contract, and reset monthly rather than quarterly, so that neither of us is arguing over a stale reference. Then put a collar on it, a cap and a floor around the base rate. My opening position, and it is a negotiating position rather than a rule, is a cap around 15 percent above the base and a floor around 10 percent below. What I am buying with that collar is not a cheaper average. It is a budget I can forecast, and a forecastable budget is worth more to a finance director than a rate that might turn out lower.

One more note on what to ask for, because asking for a smaller number in week six wastes the meeting. There are three asks that cost the other side less than a rate cut and are worth more to you. Ask for the space commitment to carry a service remedy in writing, so that if a guaranteed allocation is not honoured in a peak month you have a documented consequence rather than an apology. Ask for every surcharge outside fuel and outside the index to be listed, capped and dated, because an uncapped named surcharge is a rate increase with a friendlier name. And ask for a price-hold window on spot quotes, even a short one, so that a figure you are comparing on Monday is still valid on Friday. None of those three lowers the rate. All three lower the variance, and variance is what turns a freight budget into a surprise.

On committed volume, which is where I watch buyers lose the most money. Committed volume in peak season is how you get space, and space is the scarce thing. It is also a promise you may not be able to keep. So I would under-commit on purpose: set the minimum quantity at no more than 80 percent of my forecast, my assumption, so that if demand softens I am paying for a shortfall I can survive rather than for boxes I never filled. And I would ask for one thing in writing, which is a carry-forward: volume I did not use in one month can be applied to the next, once. Carriers are not obliged to give you that and plenty will refuse, but it is the single clause that turns a commitment from a gamble into a plan, and asking for it costs nothing.

On timing, which is the cheapest lever of all. If the road is 14 to 20 days longer than the one your calendar was built around, then your order release dates are wrong, and they have been wrong since the diversion started. For anything that has to be on a European shelf in the first week of November, I would pull the order release forward by four weeks against last year's plan and hold the goods at origin or in bond rather than paying for a premium slot in October. Four weeks is my number, derived from the 17 day midpoint plus a week of buffer, and you should argue with it using your own calendar. The point is not the exact figure. The point is that a longer road means an earlier decision, and the earlier decision costs less than the later panic.

And here is the discipline I have to enforce hardest on my own side of the house. When lead times stretch by 14 to 20 days, the instinct of a buyer is to order more, and ordering more is exactly how a two week problem becomes a two quarter problem. Every extra box ordered to make yourself feel safe lands as inventory in the quarter after the one you were worried about, which is usually the quarter when the index is falling and your competitor is discounting. Size the buffer against the spread, which on my assumptions is six days and eight boxes, and stop there. Buffer the plan, not the order book.

What would make me change this plan? The diversion share, and not the index. If the 85 percent figure starts falling, effective capacity comes back quickly, because every ship that returns to the shorter route hands back days of fleet capacity at once, and the streak breaks from the supply side rather than the demand side. I would treat a move below 60 percent as the signal to re-tender rather than to renew. On the other side, if the Panama draft limit is relaxed, the Atlantic-facing capacity eases and some pressure comes off the cost per box. I would also watch my own demand side honestly: if my sell-through is softening, the correct response to a rising index is to cut committed volume, not to argue about the rate.

There are three things that always get suggested in August and I would do none of them. I would not go fully spot in the hope of catching the turn, because a turn is visible only after it has happened and you pay for every week you were wrong. I would not sign a twelve month fixed rate simply to stop the arguments, because a fixed rate signed in week six of a streak welds the top of that streak into next year's budget. And I would not treat the freight line as the whole problem, because on this set of numbers it is not even the biggest line: 138,000 dollars a year of pipeline capital and 48,000 dollars of safety stock carrying cost both sit outside it, and both are controllable by a buyer in a way that the index is not.

On governance, because none of the above happens without it. By the end of August I want three things settled and written down. The contract-spot split, with a named owner for the spot portion and a monthly review date. The index clause, with the source, the reset date and the collar numbers typed into the contract rather than agreed over coffee. And the order-release calendar, moved forward and signed off by whoever owns the shelf date, not by logistics alone. The person who owns the shelf date is the one for whom 17 extra days either matter or do not, and if that person is not in the room when the freight contract is signed, you will sign the wrong contract very efficiently.

If I were the buyer at this table, here is the signature. Seventy percent of peak-season volume on contract with a monthly index reset and a collar of roughly plus 15 and minus 10 percent around the base. No more than 30 percent on spot, concentrated where I am genuinely flexible. Minimum quantity set at 80 percent of forecast, with a one-month carry-forward asked for in writing and counted as a win if I get it. Order releases pulled forward four weeks against last year, with the goods held at origin rather than rushed. Lead times split by routing, planned at 20 days and never at 14. And one standing instruction to my own team: the index is a direction, the diversion is the structure, and the only number I actually control is how much cash I leave on the water.

↑ Back to the key points

— By Grace Yang