Supply Chain Action Points
Read this first — the conclusion, and the moves to make:
- By Friday, ask the two carriers who covered last produce season for a written trailer count per week on your main lane for the overlap weeks, not a rate.
- Split your load list into appointment-critical and flexible; lock contracted capacity only for the critical group and keep at least 15 percent of monthly volume on spot as a pressure valve.
- Set a trigger at the dispatcher level: when same-day coverage drops below 80 percent for two consecutive days, move the next week's critical loads to contracted carriers before the Monday booking window opens.
- Add a waiting-time clause to drayage contracts this cycle, capped at two hours per stop with a defined rate after that, so shed and terminal delays stop landing on your invoice unmetered.
- Track empty-mile share weekly and keep it under 12 percent of total miles through the overlap, with a named owner on the transport side.
DAT Freight & Analytics reported dry-van spot rates climbing as the produce harvest and import-driven drayage peaks aligned, tightening equipment in key lanes. The load-to-truck ratio rose, signalling carrier pricing power returning. DAT advised shippers to lock contracted capacity early to avoid spot exposure.
The Analysis
DAT's read this week is short, and it stacks two seasons on top of each other: dry-van spot climbing as the produce harvest and the import-driven drayage peak land in the same weeks, equipment tightening in key lanes, and the load-to-truck ratio up, which is the polite way of saying carriers can ask for more.
Most desks will file this under rates. I want to file it under trailers, because a trailer sits in one place at a time and these two seasons want it in two places in the same week.
The interesting part is not that both peaks are happening. It is that they want different things from the same driver.
Two peaks, one asset. The harvest pulls dry vans out of the port metros and into growing regions, then along lanes that run to distribution centres. Import drayage pulls the same trailers back toward the ports, on appointment schedules, against a last free day. When the two calendars overlap, the number of trailers does not change and the demand for them roughly doubles in the same weeks. The ratio is the visible number. Underneath it sits a simpler fact: every trailer committed to a packing shed inland is a trailer not standing at a chassis pool.
A dry van is a box with wheels, and a driver is not interchangeable in the same way the box is. Produce shipping is loose on appointment discipline. Load times swing by hours, the shed does not run a slot system worth the name, and the driver sits. Import drayage is the opposite animal: a terminal appointment, a chassis, a gate window measured in minutes, and a last free day that starts billing the moment it passes. Put the same trailer in front of both and the market does not clear on trailer count. It clears on how much unplanned waiting a driver will absorb for the money on offer. That is why a lane can look extreme on the ratio while trailers are standing idle two counties away. The boxes are there. The willingness to sit is not.
The second physical fact is reload. A trailer that drops a produce load two hundred miles from the port has to come back empty unless somebody finds it freight. Empty miles are not free and they never appear on a rate quote. In a normal month the reload is easy, because the import flow is steady and running the other way. In the overlap weeks the reload is the same direction everybody else is running, so it collides with itself. That is the mechanism behind the ratio move. Trailers do not vanish. The productive share of them falls, because more of them are running empty in a direction that pays nothing.
The squeeze distributes by contract shape rather than by company size. An importer with a contracted drayage fleet and a fixed weekly allocation is insulated for the first weeks, right up until the carrier starts missing, and then it is worse, because there is no backup relationship left to call. An importer with a rate agreement but no committed trailer count is exposed on the first tight Monday, because a rate agreement is a price, not a truck. A small importer or a forwarder's client who needs next-day coverage buys in the worst window of the year and pays whatever the ratio says that morning. Direction matters less on this story than usual. Exporters are mostly untouched, unless they ship out of an agricultural origin, in which case they are bidding against their own harvest for the same trailers and the same drivers.
Give it two to three weeks from the first real harvest week. The signals arrive in an order, and the order is the useful part. Your drayage carrier stops confirming same-day and starts offering Thursday for a Monday request. Empty trailer availability in the port metro drops before any published number moves, because a dispatcher knows his own count before a market publishes an index. Then the terminal appointment slots get thin at the hours you actually need, which is early, because everybody wants early. The rate is the last thing to speak. By the time it does, the decision you were planning to make has been made for you by whoever booked first.
The part a ratio cannot show is that this is a driver-tolerance market wearing a trailer-shortage costume. Two consequences follow. Capacity contracted for the produce weeks is not the same capacity you need in the import weeks, because the binding constraint is a driver's willingness to wait at a shed, and that is not in a contract unless somebody wrote it in. And the shipper who loses in the overlap is not the smallest one. It is the one with a flexible last free day and no appointment leverage. That box can sit two days without a penalty, so it does sit, and the sitting shows up as a chassis pinned under it and a slot that gets harder to find on the third day. The market allocates delay to whoever can absorb it. Which is a politer way of saying it allocates delay to whoever complains last.
Assumptions below are mine, not DAT's. Take 40 dry-van loads a month across the overlap, with 30 percent needing next-day coverage, which is 12 loads. Assume next-day coverage falls by 20 percentage points once the ratio moves, so about 2.5 loads a month slip by a day. Across a 12-week overlap that is roughly 7 loads and 7 rescheduled receiving appointments. Seven out of 120 reads like noise. It is not, because a slipped load does not cost one day of one trailer. It costs the appointment, the rebooking, sometimes the sale, and a phone call to a customer who now plans around you instead of with you. The average is small and the tail is the entire story.
Without locked capacity you buy in the exact weeks the ratio peaks, which is the textbook definition of buying at the top. But locking everything is its own mistake, and a common one. Contracted trailers on lanes that never needed them are dead weight, and they are the first thing a carrier reallocates when a better customer gets desperate. The honest counterfactual is narrower than either extreme. Lock the lanes where a missed appointment carries a penalty, leave the rest on the spot market, because spot is not a failure state. Spot is the price of flexibility, and flexibility is worth real money in a season where your forecast is wrong half the time.
The trap is reading a national ratio as a local fact. Your problem is not the country's trailer count. It is the count within a two-hour radius of your origin at seven on a Monday, minus everything already committed. A carrier quoting off a load board is telling you what the board says, not what he has standing in his yard. Today's call is one question to the two carriers who covered you last produce season: how many trailers will you commit to this lane during the overlap weeks, in writing, by Friday. If the answer comes back as a rate instead of a number, you have your answer.
↑ Back to the key points