Supply Chain Action Points
Read this first — the conclusion, and the moves to make:
- Within five working days, put one question in writing to every operator you use: which parcel, which port days, and how many port hours my unit consumes; no answer on the third part means unbooked.
- Before the end of May, run a loadability review on each oversized unit covering certified lift points, pre-slinging and a lashing plan, with a target of cutting port hours per unit by at least 30%.
- Book the discharge crane and the heavy-lift road move before you book the ocean parcel, with the crane slot confirmed within three working days of vessel nomination.
- Test the container fallback once per unit type: box dimensions, permitted overhang, destination crane rating, road permit; record the answer so it stops being re-argued every shipment.
- Add one full parcel cycle rather than one week to every delivery date you quote for the next two quarters, and state that assumption in the quote itself.
The Project Cargo Journal reports the breakbulk shipper index slipped again in May as multipurpose vessel (MPV) capacity tightens and project cargo lead times lengthen. Operators cited competing demand from energy and infrastructure builds. The index signals no fast turnaround for specialised heavy-lift ocean capacity.
The Analysis
The breakbulk shipper index slipped again in May. The reason attached to it is capacity: multipurpose vessel space is tightening, project cargo lead times are stretching, and the operators say the competing demand is coming from energy and infrastructure builds. The index is being read as a sign that specialised heavy-lift ocean capacity will not turn around quickly.
An index is a summary of something physical, and the thing it summarises here is a small set of ships with cranes bolted to their decks. You cannot build one in a quarter, and you cannot conjure a heavy-lift berth where there is no crane rated for the lift. This is not a rate cycle that will normalise in six weeks. It is a shortage of deck space with a crane attached.
For anybody shipping a unit that will not go into a box, the next two quarters are a scheduling problem, not a pricing problem. Price you can hedge. A ship that is already full is not a hedge.
The facts, as given. The index fell again in May. Multipurpose vessel capacity is tightening. Project cargo lead times are getting longer. Operators attribute the demand to energy and infrastructure projects competing for the same ships. The reading is that this does not turn around soon.
Start with how a multipurpose ship actually earns. It is not a liner and it is not a bulk carrier. It carries breakbulk, project units and some containers, and it makes its money by combining parcels: several shippers, several ports, one hull. Port time is the enemy, because every hour at berth is an hour the ship is not earning and a berth another ship is waiting for. So the operator's real decision, when there is more cargo offered than deck to put it on, is not who pays most per tonne. It is who costs least per tonne in port hours. That single sentence explains almost everything that is about to happen to your booking.
Now the physical constraint, which is not the hull. A heavy unit needs four things to move, and each is a separate booking with its own lead time. It needs a lift at the loading end, either the ship's own gear or a mobile harbour crane of the right tonnage. It needs deck strength and a stow position that can take the point loads, which is a naval architecture question and takes time to answer. It needs a lift at the discharge end, and this is where most plans die, because the receiving site is often a construction plot with no crane at all and the nearest port with the right gear may be a different port from the one you booked to. It needs a road move from that port to the site, which means axles, permits and a route survey for bridges and overhead lines.
Which means the popular fallback is not a fallback. Put it in a container sounds like a way around a tight MPV market until you check three things: the internal dimensions of the box, the permitted overhang on a flat rack, and the lifting capacity at the destination. A unit that fits and can be lashed into a flat rack still has to come out of it somewhere, and the somewhere has to have a crane. If it does not, you have converted one ocean booking into a second project with its own lead time and its own failure modes. People discover this after they have already told their customer the box would sail.
Who gets hurt and who does not. A large engineering contractor with a charter or a contract of affreightment and its own heavy-lift trailer fleet is largely insulated; it bought capacity a year ago at a price that now looks clever. A mid-sized fabricator shipping three or four modules a quarter is the exposed party. It buys parcels on the spot market, it has no priority, and when two cargoes compete for the same deck it is the one that gets the polite email. A shipper with a single oversized unit is in the worst position and also the most likely to be told we will find something, which is not a booking.
Direction matters in a way that is easy to miss. Energy and infrastructure demand pulls ships toward project sites, and those sites import as well as receive domestic fabrication. So the same hull that could carry your export module out is also being bid for by an importer bringing equipment in. Both directions compete for one small fleet, and the competition is not on your lane, it is on the ship's next fixture.
When you will feel it. Quotation first, and this is the part that catches commercial teams. You cannot quote a delivery date, so you either quote late or quote a number you cannot hold. Booking second: the next available ship is not next week, it is the next parcel that has physical space for your dimensions and a stow position that works. Discharge port third, because the crane has to be reserved and the berth window has to match the vessel. Road fourth, because the permit is issued against a route and a date. Four queues, four different companies, and none of them talk to each other unless you make them.
What the index cannot show you is how the queue is actually ordered. In a tight market the operator is optimising port hours per tonne, which means the cargo that gets deferred is the cargo that is slow to load: awkward shapes, long lashing, units needing two cranes or a tandem lift, anything that requires the deck crew to stop and think. Your position in that queue is set by how annoying your unit is to load, not by what you are willing to pay. That is genuinely good news, because it is the one variable you can change without spending more.
Pre-slinging, pre-lashing, delivering as modules that bolt together on deck, certified lift points with the calculations already done, and a loading plan the chief officer can approve in an hour instead of a day, all move you up the queue. The operator will not tell you this, because from their side it just looks like your cargo is easier than the other guy's, and they will take the easier cargo at the same rate.
The second thing the index hides is the shape of the substitution ladder. There is one rung, and it is not containerisation. Above the flat-rack envelope the alternatives are other heavy-lift ship types and, for the truly oversized, semi-submersible or towed solutions, and all of those have longer lead times than the MPV you cannot get. So the ladder does not go sideways into something faster. It goes up into something slower.
Put a number on the loading question, with my assumptions and no figure from the release. Assume four units, about 90 tonnes each, moving as one parcel. Assume that loaded as-is they cost the ship two port days, because of lashing and a two-crane lift, and that pre-assembled and pre-slung they cost 0.8 of a day. Assume the vessel's port cost is around 18,000 dollars a day, which is my placeholder and not a published rate. The 1.2-day difference is about 21,600 dollars of cost that the operator either absorbs or prices into your parcel, and it is the difference between being the cargo they want on the next fixture and the cargo they defer to the one after.
Now price the deferral. Assume a parcel cycle of five weeks and six people on site at 900 dollars a day each. One bump is 25 working days of idle crew, roughly 135,000 dollars, against a freight line item that is probably a fraction of it. Those are my numbers. The asymmetry is not mine, it is just arithmetic.
Consider not doing any of this. If you book late, quote from the freight rate, and let the lashing plan be the ship's problem, nothing breaks immediately. What happens is that you get the parcel after next, your customer's site crew waits, and the delay is attributed to shipping in general, which means nobody fixes it and it happens again on the next project. The counterfactual is not a cheaper shipment. It is the same shipment, one cycle later, with the cost moved from the freight line into the project schedule where it is much harder to see and much more expensive to hold.
The trap is reading no fast turnaround as wait and it will come back, and pushing the order to the right. Capacity that is short because of energy and infrastructure builds does not clear in a quarter, it clears when those builds finish, and you do not know when that is. The second trap is quoting a delivery date off a freight quote rather than off a confirmed parcel position, which is how a shipping problem becomes a contractual one. If I had a unit to move, I would ask the operator one question today, in writing: which parcel, with which other cargo on board, and how many port hours does my unit cost you. If they cannot answer the third part, I am not booked, I am on a list, and I would plan accordingly.
↑ Back to the key points