← Back to Supply Chain Review Freight & Logistics

Carriers cancel 49 sailings through mid-September to steady rates

Source: Drewry / Linerlytica · 2026-08-11 · 17 min read
中文

Supply Chain Action Points

Read this first — the conclusion, and the moves to make:

  1. By Friday 14 August, pull forward and confirm every booking for cargo needed on the ground between 1 and 30 September, moving the booking calendar ten to fourteen days earlier than normal to survive one or two rolls during weeks 34 to 38.
  2. From Monday 17 August, maintain a weekly void tracker owned by one named person: voyages planned versus voyages still sailing per lane, four weeks forward, escalating any lane that falls below 80% of planned voyages to a routing review by Friday of the same week.
  3. Before 22 August, produce a two-column route sheet for every major inland destination: door-to-door days via West Coast plus rail versus all-water East Coast, each with the count of alternative sailings available in the same week, and shift at least 20% of East Coast volume to the option with more alternatives.
  4. Write down the air-freight test before any emergency: with sea all-in near 11,000 dollars per 40ft on 12 tonnes and air assumed at 4.5 dollars per kilogram, fly only when the cost of arriving late exceeds 43,000 dollars per box, and review that threshold monthly against your own quotes.
  5. Raise safety stock to five weeks of cover for the 17 August to 20 September window and hold the extra cover at a West Coast DC with more feeding sailings; start the review on 21 August and complete it before week 38 closes.
  6. Use existing contract coverage for August and September, hold spot share to no more than 30% of volume during the void window, and open the next round of annual talks in the last week of September rather than signing inside weeks 34 to 38.
Skip to the detailed analysis ↓
Summary

Drewry's Cancelled Sailings Tracker shows 49 blank sailings planned from week 34 (17 Aug) to week 38 (20 Sep), a 7% cancellation rate, as lines manage capacity into peak season. Transpacific space remains tight, with Asia-US East Coast spot rates forecast to breach $8,500 per 40ft.

The Analysis

Week 34 begins on 17 August. Week 38 ends on 20 September. Between those two dates Drewry's cancelled sailings tracker is showing 49 voyages that are not going to sail, which works out at a 7% cancellation rate across the major east-west trades. A 7% number sounds like nothing at all until you are the shipper whose sailing sits inside that 7%. I have stood in a booking office in the middle of a blank sailing programme and watched a perfectly ordinary booking turn into a two week problem, and what made it a problem was never the rate. It was that nobody had written down, before the ship disappeared, what to do when it did.

Read the number properly before you relax. Seven percent cancelled means ninety-three percent still sailing, and that is the sentence the carriers will give you, and they are not wrong. But an average across five weeks and three trades hides the only figure that matters to you, which is your loop, your week, your port pair. If the service you use runs three sailings a month and one of them is voided, your cancellation rate is not 7%, it is 33%, and your planning has to be built on your own number rather than on the headline.

The second thing in this item is where the pressure is pointing. Transpacific space stays tight, and the forecast for Asia to U.S. East Coast spot is that it breaks through 8,500 dollars per 40ft. I am not going to spend this piece on the rate itself. What I care about is what a tight eastbound transpacific does to the shape of your route sheet, because in a blank sailing month that is where the money actually gets lost or saved, and it is the part of the problem you can still do something about on a Tuesday afternoon.

A blank sailing is not a delay, and the difference matters more than it sounds. A delay is a ship that turns up late. A blank sailing is a ship that does not exist. When a voyage is voided the carrier does not simply move your booking to the next column on the sheet. The rotation gets re-cut. Sometimes a port call is dropped entirely, which means your box discharges somewhere else and finishes the trip on a feeder or on a rail car that nobody quoted you. The departure date moves, the cut-off moves with it, and the clock on your free time starts in a place you did not plan for. On a highway this is a lane closure plus an exit you did not know was yours.

So the first habit to build for these five weeks is to stop planning against a transit number and start planning against a sailing. Transit is how long the journey takes once you are on it. The sailing is whether the journey happens at all this week. I keep a sheet with the actual voyages I depend on, by week number, with the void status updated every Monday, because the tracker publishes a count and I need a schedule.

Now run the arithmetic backwards, which is where most September plans quietly fail. Suppose your all-water Shanghai to Savannah door-to-door is 32 days in normal conditions. I am putting that number here only so the method is visible, and you should replace it with your own average from the last quarter, because my transit is not your transit. To land goods in a Georgia DC by 20 September, the box needs to sail around 19 August. Week 34 begins on 17 August, and that is exactly where the void sailings start. Now assume one roll. One roll on a weekly service is seven days, so to survive a single roll you need to be on a sailing around 12 August, which means a confirmed booking in the week you are reading this. Assume two rolls and you are already outside the window. That is the arithmetic people skip, and it is the reason September cargo gets stuck in a yard with nobody able to say whose fault it was.

The consequence is unglamorous and it is the whole point. For anything you need on the ground in the second half of September, pull your booking calendar forward by ten to fourteen days against what you would normally do. Not because the voyage is slower, but because the voyage might not be there, and the only defence against a missing ship is being on an earlier one.

Then look at the shape of your route, because this is the part where a tight eastbound transpacific actually changes what you should do. There are two roads from Asia to the American East Coast and everybody knows both. One stays in the water all the way round to Savannah, Charleston, Norfolk or New York. The other gets out at Los Angeles, Long Beach, Oakland or Prince Rupert and puts the box on a train for the rest of the way. In a month when eastbound transpacific is the tight trade and the East Coast is the one being talked about, the land bridge deserves a hard look, and not only for money reasons.

It deserves a look because of fallback density. A coast with more loops gives you more alternative sailings when one is voided, and in a blank sailing month the number of alternative sailings you can reach is worth more than the transit difference between the two roads. Sit down and count them. For each inland destination you serve, write two columns: door-to-door days via the West Coast plus rail, and door-to-door days all-water to the East Coast, and next to each write how many alternative voyages exist in the same week if your first choice is voided. The second column is the one that decides things in weeks 34 to 38.

Do not underestimate the smaller gateways on either coast while you are doing that count. I have moved cargo through Charleston when Savannah was full and through Norfolk when New York was tight, and both times the saving was in days rather than in money. I have also watched a plan like that fall apart because the drayage partner did not serve the second port and nobody checked before the booking was made. A second gateway is a spare tire. Before you rely on it, confirm three things in writing: that your trucker serves that terminal, that your DC can receive on the days it will actually arrive, and that the rail ramp you would use has a rate filed and a slot available.

There is a third road that gets overlooked on the U.S. side, and it is the one through Mexico. Manzanillo and Lazaro Cardenas with a rail crossing north can be a genuine answer for Texas and for parts of the Midwest, and 49 void sailings on the mainstream east-west loops is a reasonable moment to find out whether it works for you. The cost of finding out is not trivial: a border crossing adds a party and a set of procedures you may not have today, the rail product is different, free time is different, and the customs point moves. Test it on one lane in a month when you can absorb a bad fortnight, and do not put your most time-sensitive customer on the first attempt.

Then the question of changing mode, which is the one that gets asked in every meeting and answered badly. Here is how I price it, with the assumptions written out. Assume one 40ft box carries 12 tonnes. Assume your all-in sea cost to the East Coast is 8,500 plus 2,500 of inland, so 11,000 dollars, which works out near 0.92 dollars per kilogram. Assume an air rate of 4.5 dollars per kilogram, which is an assumption and not a quote, so check it before you do anything with it. Twelve tonnes by air at that rate is 54,000 dollars. The gap against sea is about 43,000 dollars per box.

That 43,000 is the real question, and it is a question about your business and not about freight. Air is justified on this lane when the cost of arriving late exceeds that number. A production line down at a plant that loses 20,000 dollars an hour justifies it inside two days. A promotional shipment that misses a shelf window by a week usually does not. Write the threshold down before the emergency, because in the emergency nobody does arithmetic, they just say yes to the fastest option and discover the invoice in November.

Inventory is the other lever, and in a five week void programme it is the cheapest one. If the disruption window runs from 17 August to 20 September, then whatever you need in that window should already be moving, or already landed, before the middle of August. For anything you cannot move early, raise the cover: I would rather carry five weeks of safety stock through this window than three, and I would rather hold it in a West Coast DC that has more sailings feeding it than in an East Coast one that does not. Carrying two extra weeks costs you warehouse space and cash. Missing a week of supply in the middle of a cancellation programme costs you a customer, and those two costs are not the same size.

Now the contract calendar, because the timing mistake here is expensive and common. In a month when space is tight, contract coverage is worth more than it is in any other month, and not because of the rate it contains. It is worth more because a volume commitment puts you ahead of spot cargo when a sailing is oversubscribed or voided. If you have a contract, use it now. Book against it, take the allocation, and stop treating it as a price you compare against the spot market each week.

But do not sign a new annual agreement inside weeks 34 to 38. That is the seller's market, and the week you need space most is the worst week in the year to negotiate for it. My own calendar is to run August and September on existing contract coverage plus a controlled slice of spot, then open the next round of talks in the last week of September once the void programme has run out and capacity is being reinjected, and close it in October against real numbers rather than against a forecast. The 8,500 figure is a forecast. A forecast is not a rate card, and planning a budget on it as though it were a quotation is how people end up arguing with their own finance team in November.

Build your own cancellation tracker in the meantime. The published 7% is an average over trades and weeks, and averages are for people writing headlines. What you need is the count on your own services, four weeks forward, updated weekly. Assign it to one person, give them a Monday morning slot, and make the output a single number per lane: how many of the voyages you planned to use in the next four weeks are still sailing. When that number drops below about 80% on a lane, that lane goes on the escalation list and gets a routing review before Friday.

Rolling is where the operational pain concentrates, so understand the queue. When a sailing is voided, the cargo on it has to go somewhere, and it goes in an order: contract cargo with a volume commitment first, contract cargo without one next, spot cargo after that. If you are on spot this month you are in the last group, which means two things in practice. Book earlier than feels reasonable, and ask the question nobody asks at the booking desk: what exactly happens to my booking if this sailing is cancelled. Ask whether it rolls to the next voyage or returns to the pool. Ask who absorbs the dwell. Ask whether the rate you were quoted survives the roll or is re-priced on the new departure date.

Free time is the second place the money goes. During a cancellation programme terminals fill with rolled boxes, and a yard that is full is a yard that gets strict. The free days you were working with in July may not be the free days on offer in week 36. Get the current number in writing for each gateway you use, find out which event starts the clock, and remember that the terminal clock and the box clock are two different clocks with two different tariffs. If you have to choose where to let a box sit during this window, choose the cheaper clock, and make sure the person booking the appointment knows which one that is.

Beware the products that appear in a month like this. Guaranteed space, priority loading, premium protection: they all exist, they all have a price, and some of them are worth it. Ask what exactly is guaranteed and what happens when the guarantee fails. If the answer is a refund of the premium and nothing more, you have not bought space, you have bought a partial rebate on being late, and that is a different product from the one the name suggests. Price it against the 43,000 dollar air gap and against the cost of two extra weeks of safety stock, and you will usually find the boring answer wins.

Watch the minimum quantity commitment while the sailings are thin. If void voyages make it hard to lift the volume you committed to, you may end the year short of your tier, and the shortfall gets priced at renewal. Track committed volume against actual lifts weekly through this window, and if you are going to miss, tell the carrier in September rather than in the renewal meeting. Carriers remember who told them early.

Changing where you buy is the slow answer and it is not a five week answer, but a programme like this is a reasonable moment to start measuring it. Count sailings per week out of any origin you are considering, not just the price. A weekly service loses fourteen days to a single cancellation. A service running four times a week loses three. Over a five week window with 49 cancellations in the market, that difference is the entire plan.

One more point on the two roads, because it decides more cases than people expect. The land bridge is not automatically the answer just because the East Coast is tight. If your distribution centre sits within a two hour drive of Savannah or Norfolk, all-water still wins on nearly every measure you care about, and a void programme does not change that. The land bridge wins for destinations in the middle of the country and for cargo that genuinely has a fallback problem at the East Coast gateways. Sort your destinations by drive time from the East Coast port before you move anything, and only move the ones that are properly inland.

A detail that gets forgotten while everybody is watching the water is that the inland side has to absorb the diversion. Boxes that were going to Savannah and come through Los Angeles instead land on the same rail ramps and the same drayage pool that everyone else is already using, and that network was not sized for an extra week of volume. Ramps tighten, appointments get pushed out, and the dwell you saved at sea reappears on the ground, usually with a detention bill attached. When you switch a road during a void programme, book the inland leg at the same time as the ocean leg rather than after the ship sails, and ask the ramp for a slot instead of assuming one is there.

The last detail is less operational and more commercial, and it is the one that separates the shippers who handle this well from the ones who do not. Tell your own people early. Sales usually finds out about a slipped sailing from an unhappy customer roughly three weeks after the booking desk knew. Put one line in the weekly report, planned voyages against sailing voyages per lane, and let the account managers read it. It takes five minutes to produce and it prevents the worst conversation there is, the one where a customer learns the bad news from an arrival date rather than from you. Over a five week programme with 49 cancellations in the market, being the shipper who called first is worth more than any routing trick in this piece.

There is one more thing worth saying about how this ends. Void programmes are a capacity management tool, and they end when the reason for them ends. Week 38 closes on 20 September. Carriers reinject capacity when the peak passes, and the space that was impossible in week 36 is often available in week 40. If you have cargo that can wait, price the wait. Do not buy panic space in week 35 for something that does not need to be on the ground until late October, because you will be competing with everyone else who panicked in the same week, and you will be paying for a problem that solves itself.

So the week itself, for an import desk reading this on 11 August. Four things, and all of them are boring. Pull September bookings forward by ten to fourteen days and get them confirmed this week. Count alternative sailings per destination and put the count next to the transit time, because for the next five weeks the count is the more important number. Decide now, on paper, what you will air-freight and what you will not, using the 43,000 dollar gap per box as the test. And write down who updates the void tracker every Monday and what they do when a lane drops below 80% of planned voyages.

None of this is clever, and that is the point. A cancellation programme is not a puzzle to solve, it is a ferry timetable that has lost some of its crossings. You do not argue with the ferry, and you do not renegotiate with the tide. You take an earlier crossing, you know which other harbour also has a boat, and you decide in advance what your cargo is worth enough to fly. Week 34 starts in six days. Check the timetable today, not on the morning your truck is already on its way to the terminal.

↑ Back to the key points

— By Ömer Kaya