Xeneta put Asia-US West Coast rates at $7,295/FEU in week 35, up more than 20% month-on-month, while Asia-Europe fell about 11% over the same period. The spread between US coasts has widened to over $3,300 per container (roughly $7,200 west vs $10,500+ east). Drewry's WCI shows the same split as carriers defend Pacific rates and Suez return pressure hits Europe.
The Analysis
Xeneta puts Asia to US West Coast rates at $7,295 per FEU in week 35, up more than 20% month on month, while Asia to Europe fell about 11% over the same period. The spread between the two US coasts has widened past $3,300 a container, with the West around $7,200 and the East above $10,500. Drewry's World Container Index shows the same split: carriers are defending Pacific rates while the prospect of a Suez return presses on Europe. For anyone moving boxes into North America, that is not a market report. It is a routing and pricing instruction.
Read the direction of travel first. A 20% month-on-month rise on the West Coast compounds on a base that is already high, and the East Coast premium of more than $3,300 is what a single port decision now costs. Europe is the mirror image, down 11%, which makes it the cheaper lane for anyone whose cargo can actually go there.
Every group below works from the same figures: $7,295 per FEU to the US West Coast, above $10,500 to the US East Coast, a gap of more than $3,300, and a US East Coast rate roughly 44% above the West. Assumptions are stated wherever a calculation is used.
For Exporters
- By 25 September, requote every open US offer as three lanes (West Coast, East Coast, inland) with a 14-day validity and a stated FAK or named-account basis
- Size the split: 20 East Coast containers at a $3,300 gap is $66,000 a month and $792,000 a year gross, or $30,000 a month and $360,000 a year net after $1,800 a container of West Coast inland cost
- By 5 October, move every order that can take a West Coast gateway plus a rail leg onto that routing before the month-end cut-off
- Put a bunker and peak-season clause with a stated trigger and notice period in every CIF and DDP offer
- Price transshipment honestly: a $1,200 a container saving is $24,000 a month on 20 boxes, against 10 extra transit days and origin risk if the goods fall under a US trade-remedy order
- Never quote one global US rate when the two coasts differ by 44%, and keep origin documents matched to the declared route
Your quote has an expiry date on it, and week 35 just reset the number behind it. Asia to US West Coast is at $7,295 per FEU, up more than 20% month on month, while the US East Coast sits above $10,500, a spread of more than $3,300 a container. Sell FOB and the gap belongs to your buyer, and the argument becomes about your ex-works price. Sell CIF or DDP and it is your number to hedge, which means the validity window on your offer is now a commercial decision rather than a formality. Nothing in the week 35 data suggests the West Coast number is about to fall back.
Size the decision. Assumptions: 40 FEU a month to the United States, 20 of them to the East Coast, a West Coast rate of $7,200 and an East Coast rate of $10,500. Moving those 20 containers to the West Coast saves $3,300 a box, or $66,000 a month and $792,000 a year. The offset is inland transport. Assume a West Coast to inland destination rail and drayage leg of $1,800 a container: $36,000 a month, which leaves a net $30,000 a month and $360,000 a year. That net figure is what belongs in front of your buyer, not the headline spread.
By 25 September, requote every open US offer on a lane basis, West Coast, East Coast and inland, instead of one US price, and cap the validity at 14 days with a stated FAK or named-account basis. By 5 October, move any order that can accept a West Coast gateway and a rail leg onto that routing before the month-end booking cut-off. Put a bunker and peak-season clause in every CIF and DDP offer, with the trigger and the notice period written out. Keep origin and shipping documents aligned with the declared route, because a re-routed consignment still clears on the same origin evidence.
Alternatives and what they cost. A US East Coast routing via a third-country transshipment can narrow the gap: assume a $1,200 a container saving against $10,500, so $24,000 a month on 20 boxes and $288,000 a year, against about 10 extra days of transit, which on $40,000 of cargo value a container and a 6% cost of capital is roughly $1,300 a year for those 20 boxes. The arithmetic favours it and the risk is not financial. A box that touches a third country without substantial transformation can raise origin questions in a US trade-remedy case, and transshipment space is the first thing to disappear in a peak. The other trap is quoting one global rate when your two coasts differ by 44%.
For Cross-Border E-commerce
- By 30 September, rebuild landed cost per SKU on the actual gateway rather than a US average, and flag every SKU where freight moved more than $1.00 a unit
- Quantify the lane choice: 3,000 units a container at $2.43 versus $3.50 a unit is $1.07, so $64,200 a month and $770,400 a year at 60,000 units a month
- By 10 October, move the highest unit-freight SKUs to a West Coast gateway plus rail and keep only fast-replenishment SKUs on the East Coast
- Cut the winter buy on any SKU whose contribution margin falls below 15% at the East Coast rate
- By 31 October, renegotiate last-mile and returns cost with the 3PL on a West Coast primary flow, allowing two extra days for the rail leg
- Do not set retail prices on a West Coast freight assumption while containers discharge on the East Coast
Freight is a per-unit cost in your margin, and this gap is large enough to move a SKU from profitable to marginal. Asia to US West Coast at $7,295 per FEU against a US East Coast above $10,500 is more than $3,300 a container, which on a 3,000-unit container is $1.10 a unit you never budgeted for if your cost model assumed the West Coast. Asia to Europe is down 11% over the same period, which makes a European inventory position cheaper this month than it was last month.
Assumptions: a container of 3,000 units, a West Coast rate of $7,295 and an East Coast rate of $10,500. Freight per unit is $2.43 on the West Coast and $3.50 on the East, a gap of $1.07 a unit. At 60,000 units a month that is $64,200 a month and $770,400 a year of cost difference. Now test the restock decision against it: reordering one hero SKU 10 days earlier through a West Coast gateway holds an extra 20,000 units at a $12 landed cost, or $240,000, which at a 6% cost of capital is $14,400 a year, against the $64,200 a month the same routing decision saves.
By 30 September, rebuild the landed cost per SKU on the actual gateway rather than a US average, and flag every SKU where freight moved more than $1.00 a unit. By 10 October, move the SKUs with the highest unit freight burden onto a West Coast gateway and a rail leg, and keep only the fastest-replenishment SKUs on the East Coast. Cut the winter buy for any SKU whose contribution margin falls below 15% at the East Coast rate. By 31 October, renegotiate last-mile and returns cost with your 3PL on the assumption that the West Coast flow is now the primary one, because a rail leg adds two days to the promise.
Alternatives. A European flow is genuinely cheaper this month, but only for goods already sourced there. Splitting a seasonal buy across both coasts hedges the gap in both directions and doubles the number of inbound flows to manage. Holding more stock protects service and ties up cash at the numbers above. The traps: quoting a landed cost on a US average when the coasts differ by 44%; ignoring that a rail leg adds roughly two days and can change the returns path; and setting a retail price from a West Coast assumption while every container discharges on the East, which is how a 12% freight move becomes a 4% margin loss no one can find.
For Manufacturing Plants
- By 30 September, put a gateway assumption into the standard cost of every imported part and re-run build cost at $7,295 and at $10,500 a container
- Qualify a West Coast transload or rail route by 15 October for every part where the gap exceeds 20% of that part's landed cost
- Size the trade: three containers a week at a net $1,500 each is $19,500 a month and about $234,000 a year, against $15,000 a year for five extra days of in-transit stock
- By 31 October, move parts that can take five extra transit days onto the West Coast flow and raise their in-transit buffer from 7 to 12 days
- Keep the East Coast flow for critical-path parts and pull long-lead spares to a 90-day horizon
- Never run the same safety stock on both routes when one lane costs $3,300 more per container
Your inbound materials and components are costed on a US average that no longer exists. Asia to US West Coast is at $7,295 per FEU, up more than 20% month on month, the East Coast sits above $10,500, and the gap is more than $3,300 a container. For a plant importing parts on a four-week cycle, that gap is the difference between a West Coast transload and a direct East Coast discharge, and it is already inside the standard cost your quoting team is using today.
Assumptions: three inbound containers a week, all currently through the US East Coast, a West Coast rate $3,300 lower, and an inland rail and drayage leg of $1,800 a container, so a net $1,500 a container. Three containers a week is about 13 a month, so the net saving is $19,500 a month and roughly $234,000 a year. Against that, a West Coast routing adds five days of transit, which on $50,000 of daily material consumption is $250,000 of extra in-transit inventory, about $15,000 a year at a 6% cost of capital. The route still pays, and the buffer needed to keep the line running is the real negotiation.
By 30 September, put a gateway assumption into the standard cost of every imported part and re-run the build cost at $7,295 and at $10,500 a container. By 15 October, qualify a West Coast transload or rail route for every part number where the gap exceeds 20% of that part's landed cost. By 31 October, move the parts that can take five extra days of transit onto the West Coast flow and raise the in-transit buffer from 7 days to 12 on those parts only. Keep the East Coast flow for parts on the critical path, and pull long-lead spares to a 90-day horizon so a routing change does not become a line stop.
Alternatives, ranked by cost. A West Coast gateway plus rail is the cheapest structural fix and needs a buffer. A third-country transshipment narrows the East Coast gap but adds a handover and origin documentation. Air freight covers a gap in the build, not a $3,300 routing difference, and at three containers a week it is unaffordable. Holding more inventory on both coasts is the most flexible option and the most expensive in cash. The traps: costing parts on a national average; forgetting that the rail leg adds about five days at the inland end rather than two; and running the same safety stock on both routes, so the cheaper lane carries the same buffer as the expensive one.
For Brand Owners
- By 30 September, publish price and delivery by region rather than nationally, and set a separate East Coast price where the freight gap exceeds 30% of landed cost
- Quantify the routing gain: $30,000 a month net is about 3,676 units a month, or 44,000 units a year, held at current price at $8.16 of gross profit a unit
- By 15 October, set a written channel and region inventory priority, since a $3,300 gap makes the same stock worth more in one region
- Put a freight-index clause with a stated trigger and a 30-day notice period into every annual customer agreement
- From 1 November, hold the East Coast promotional calendar flat until the Q1 rate picture is visible
- Never treat the $3,300 headline gap as the saving when $1,800 a container goes back into inland transport
A $3,300 a container spread between the US coasts is a pricing input, not a logistics detail. With Asia to US West Coast at $7,295 per FEU, the East Coast above $10,500 and Asia to Europe down about 11%, the cost of the same product differs by more than 44% depending on where it lands. A brand that prices on a national average is undercharging on one coast and overcharging on the other, and one of those two errors shows up immediately as margin while the other shows up slowly as lost share.
Assumptions: 40 containers a month, 20 discharging on the East Coast, a West Coast rate $3,300 lower, and a West Coast inland leg of $1,800 a container. Gross saving is $66,000 a month; net is $30,000 a month and $360,000 a year. Convert that to price. At $8.16 of gross profit a unit, $30,000 a month holds the current price on roughly 3,676 units a month, or 44,000 units a year. That is the size of the price promise one routing decision funds, and it is a promise you can make on the West Coast that you cannot make on the East at the same rate.
By 30 September, publish price and delivery by region rather than nationally, and set the East Coast price separately where the freight gap exceeds 30% of landed cost. By 15 October, set a written channel and region inventory priority, because a $3,300 gap means the same stock is worth more in one region than the other. Put a freight-index clause with a stated trigger and a 30-day notice period into every annual customer agreement. From 1 November, hold the promotional calendar flat in the East Coast region until the Q1 rate picture is visible, because a discount in the region carrying the highest freight cost is a direct margin transfer.
Alternatives. Keep a European inventory position where the goods are already sourced there, since that lane fell 11% and is the cheapest of the three. Absorb the gap on the top two SKUs and re-price the tail, which protects volume where it matters and margin where it does not. Move the pack rather than the price. The traps: a national price list against a 44% regional freight difference; an annual customer agreement with no freight-index clause, which turns every future rate move into your own cost; treating the West Coast net saving as $3,300 a container when the inland leg takes $1,800 of it back; and letting a Q4 promotion run in the region with the widest gap.
For Procurement Teams
- By 30 September, split every ocean tender into two US lanes with separate volumes, separate rates and a gateway-substitution clause allowing 30% of volume to move on 14 days' notice
- Quantify contracted cover: 60% at $6,800 against $7,295 spot saves $495 a box, or $11,880 a month on 24 containers
- Show the asymmetry: a further 20% rise to $8,754 lifts the same contract saving to $1,954 a box, or $46,896 a month, which is why cover goes from 60% to 75% by 15 October
- By 31 October, qualify one transshipment option for East Coast volume and price it against the $3,300 gap including extra handovers and origin evidence
- Tender in November for a January start, with an index-linked escalator that has a stated cap and floor, instead of buying spot in February
- Do not sign a contract that names a port but not a gateway, and never treat a $3,300 headline gap as net when $1,800 goes back to inland transport
Procurement owns the two decisions this rate gap creates: which lane each volume sits on, and how much of it is contracted rather than bought on spot. Asia to US West Coast is at $7,295 per FEU, up more than 20% month on month, the East Coast is above $10,500, the gap is over $3,300, and Asia to Europe is down about 11%. A single global rate card cannot survive those numbers, and neither can a contract that fixes volume by port without a gateway-substitution clause.
Assumptions: 40 FEU a month, 60% contracted at $6,800 a FEU and 40% bought on spot at the current $7,295 West Coast rate. The contract saves $495 a box on 24 containers, or $11,880 a month. Now price the risk. If the West Coast spot rate rises another 20% to $8,754, the contract saving on the same 24 boxes becomes $1,954 a box, or $46,896 a month, so the value of contracted cover rises roughly four times on a 20% move in spot. That asymmetry, not the headline gap, is the argument for lifting contracted cover from 60% to 75% before the peak.
By 30 September, split every ocean tender into two US lanes with separate volumes, separate rates and a gateway-substitution clause that allows up to 30% of volume to move between coasts on 14 days' notice. By 15 October, lift contracted cover from 60% to 75% on the lane where the spot curve is steepest, and replace a fixed annual rate with an index-linked escalator that has a stated cap and floor. By 31 October, qualify one transshipment option for East Coast volume and price it against the $3,300 gap, including the extra handovers and the origin evidence it requires. Fix the negotiation calendar now: tender in November for a January start, rather than buying spot in February.
Alternatives and the trade-offs. Route volume through a third country to close the East Coast gap: a $1,200 a container saving is $24,000 a month on 20 boxes, against roughly 10 extra transit days and a real origin question if the goods sit under a US trade-remedy order. Shift volume to Europe, which is 11% cheaper, but only if the demand is actually there. Buy more spot and stay flexible, which is the most expensive option when the curve is rising 20% a month. The traps: a contract that names a port but not a gateway; an index clause with no cap, which simply passes the peak through to you; and treating the $3,300 headline gap as the saving when the inland leg takes $1,800 of it back.