← Back to Supply Chain Review Ports & Infrastructure

Kuehne+Nagel flags Manila, Lazaro Cardenas among worst port waits in early July

Source: Kuehne+Nagel · 2026-07-06 · 7 min read
中文

Supply Chain Action Points

Read this first — the conclusion, and the moves to make:

  1. Re-plan Q3 Philippines-lane schedules with one week of added slack in the second week of July, and require the forwarder to state the expected waiting time in the booking confirmation for each sailing.
  2. Decide the German-inland routing before week 30: compare Hamburg plus barge, Antwerp plus barge, and Antwerp plus full-road options on total days and cost, and complete the analysis by July 18.
  3. Add MICT yard occupancy, Rhine water level, and Antwerp waiting time to a weekly dashboard; two consecutive weeks of MICT occupancy above eighty-five percent triggers the alternate-hub plan.
  4. Build a one-sailing buffer into Q3 northern-Europe bookings so a queue-triggered missed connection does not cascade into a missed delivery date, with the buffer owned by the logistics manager.
  5. Ask your forwarder to flag any Q3 sailing where the port call has been dropped or consolidated, so feeder dependencies are known at booking rather than at the quay.
Skip to the detailed analysis ↓
Summary

Kuehne+Nagel's 7-14 July port update reported 7-day average vessel waiting times of 4.69 days at Manila (MICT yard at 85-90%), 3.5 days at Lazaro Cardenas, 2.02 days at Antwerp, 1.81 days at Rotterdam and 1.5 days at Busan. Low water on the Rhine is restricting access to Dusseldorf and Cologne, with no improvement expected before week 30.

The Analysis

The latest weekly port update, covering July 7 through 14, puts Manila at 4.69 days of average vessel waiting time and Lazaro Cardenas at 3.5. Antwerp sits at 2.02, Rotterdam at 1.81, Busan at 1.5. And tucked at the bottom of the same report, low water on the Rhine is restricting access to Dusseldorf and Cologne, with no improvement expected before week 30.

Two stories live in one page. One is the familiar queue at Asian and Latin American gateways. The other is the one that actually hurts: ships can reach Hamburg or Rotterdam, but the cargo behind them cannot reach the German inland it was booked for. A vessel waiting at anchor costs a schedule; a barge that cannot sail costs a warehouse.

What follows reads the numbers as a shipper should: which waits are structural, which lanes need a week added to the plan, why the leading indicator is yard occupancy rather than the waiting figure itself, and where the report's own method leaves you blind.

Read the numbers in the order that explains them. Manila tops the list at 4.69 days of seven-day average waiting, and the same report tells you why: the MICT yard is running at eighty-five to ninety percent occupancy. That pairing is not a coincidence. A full yard slows the box-shuffling cycle, a slow cycle stretches vessel turnaround, and stretched turnaround queues the next ship at anchor. Congestion at a container terminal is a throughput disease wearing a berth symptom. Lazaro Cardenas at 3.5 days is the same disease at a different latitude, a gateway whose yard and landside capacity have lagged its volume for long enough that the wait has become structural rather than seasonal. Northern Europe shows a milder version: Antwerp at 2.02 days and Rotterdam at 1.81 are not crisis numbers, but they sit above the comfortable band, and the yard occupancy figures from the same ports confirm the pressure is real. Busan at 1.5 days is what a healthy hub looks like when everything is working.

Why this particular week runs hot has three currents crossing. It is July, the pre-peak push before the autumn retail build, and forwarders are booking ahead of schedule. Manila's congestion has been building on its own logic for months, so the seasonal push lands on a system already near its ceiling. And the Rhine is low, which does not affect a single vessel's waiting time but removes inland capacity across northwestern Europe at exactly the moment ocean carriers are already arriving late. When the ocean leg and the inland leg are both degraded, the failure shows up as a missed delivery date, not as a port statistic, and by then no one can say which leg caused it.

Impact distributes unevenly, and the uneven part is what to plan around. Philippines-lane shippers take the direct hit: four-point-six-nine days of average waiting means your transit plan needs a full week of slack added, and small shippers without volume leverage absorb it entirely into inventory cost. The Mexico lane feels it through Lazaro Cardenas, where a 3.5-day wait inflates every Asia-Mexico transit by a similar margin. The German inland is its own category, and the sharpest one: a container that discharges at Hamburg or Rotterdam on time can still sit for days waiting for a barge slot, because low water restricts loading drafts on the Rhine.

A practical way to size it: add roughly two days for the elevated berth wait in the northern range ports, plus one to three days of inland drag on the Rhine, and a shipment into Dusseldorf or Cologne should be planned four to five days longer than the clean-weather schedule, with the caveat that this estimate assumes current water levels hold. Inland distributors running just-in-time replenishment are the least equipped to absorb that, because their entire cost model assumes the schedule they signed.

Timing gives you a little more room than the waiting numbers suggest, but not much. The waiting figures describe the past seven days, so they are already embedded in any quote you are getting now; the question is how long they persist. The port update itself draws one line for you: no improvement on the Rhine before week 30, which puts the earliest realistic relief around July 20. Anything you book this month for August arrival into the German inland should be quoted and planned as if the constraint is still active, because it is. The Manila wait, by contrast, has no stated end, and the honest planning assumption is that it lasts at least through the pre-peak season. Your lead time is measured in weeks: decisions about August cargo are being made now against conditions that will not have changed by the time the vessel sails.

Here is the part that gets skipped when people read these updates like weather reports. The first pattern is that congestion is migrating, not disappearing: Manila and Lazaro Cardenas have been elevated for months, and Antwerp and Rotterdam were never really resolved. Treating each weekly report as a fresh event means re-learning the same map every week instead of planning on it. The second signal is that yard occupancy is the leading indicator, and the waiting time is the lagging one. MICT at eighty-five to ninety percent tells you next week's queue is already loaded; by the time the waiting figure prints, the cost is in your invoice.

A shipper who tracks occupancy gets a week of warning a shipper who tracks waiting time does not. The third pattern, least visible of all, is that when ports back up, carriers protect schedules by dropping calls on smaller ports and consolidating into the bigger ones. That is efficient for the vessel and quietly expensive for you, because a box that used to load direct now waits for a feeder, and the report will never mention your port at all.

The contrary case is simple and worth holding. If the autumn peak does not materialize, or if Asian export growth cools through the third quarter, these queues drain on their own by August or September and the whole story evaporates without anyone doing anything. If instead the peak lands on top of existing structural congestion, the two-day waits in northern Europe can double, and the difference between a bad week and a bad quarter is one variable: how much volume shows up. The condition that flips the picture is public and checkable every week: yard occupancy at MICT and the Rhine water level. Those two numbers, not the waiting-time headline, decide whether your August plan holds.

↑ Back to the key points

— By Tomás Ferreira

port waiting timeManilaLazaro CardenasAntwerpRhineKuehne+Nagel